Issue details

M5 Junction 10 Improvement Scheme; Revenue budget approval and Homes England contract conditions agreement

To ask Cabinet to delegate authority to the Cabinet Member; Environment and Planning in consultation with the Executive Director Economy, Environment and Infrastructure, the Executive Director Corporate Resources and S151 Officer to enter into a Grant Determination Agreement (GDA) with the Ministry of Housing Communities and Local Government (MHCLG) for the M5 Junction 10 scheme and to authorise revenue and capital financial support for the project until the J10 GDA is signed and; to authorise continued expenditure on the M5 J9/A46 project.

 

Please note:

 

In accordance with Regulation 4(2)(b) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012, the public may be excluded from the meeting for this item of business because it is likely that, if members of the public were present, there would be disclosure to them of exempt information, and the public interest in withholding this information outweighs the public interest in disclosing the information to the public.

The reason for the information being private is because ‘the relevant information relates to the financial or business affairs of a particular person (including the Authority holding that information) Paragraph 3, of Schedule 12A of the Local Government Act 1972’.

Representations requesting that the Authority give consideration to making the associated reports and any other documents relating to this matter accessible to the public should be received 7 clear days before the decision is to be taken. Any representations should be made in writing to the Chief Executive, (marked for the attention of Jo Moore, Democratic Services Unit, email: jo.moore@gloucestershire.gov.uk ) by 5.00pm on Tuesday 9 June 2020.

Decision type: Key

Reason Key: Expenditure > £500,000 and 2 Divisions affected;

Decision status: For Determination

Notice of proposed decision first published: 19/05/2020

Anticipated restriction: Fully exempt  - View reasons

Decision due: 17 Jun 2020 by Cabinet

Lead member: Cabinet Member - Environment and Planning

Contact: Simon Excell, Lead Commissioner Strategic Infrastructure Email: simon.EXCELL@gloucestershire.gov.uk Tel: 01452-428487.

Consultees

GCC Strategic Communities and Infrastructure Members Board (SCIMB)
Tewkesbury Borough Council
Cheltenham Borough Council
Gloucester City Council
GFirst LEP
Ministry for Housing, Communities, Local Government (Cathy Francis, Director of Land and Housing Delivery and (then) Secretary of State James Brokenshire)
Homes England
Highways England
MP’s Laurence Robertson, Alex Chalk, Richard Graham
Department for Business, Energy and Industrial Strategy

Scrutiny Input: None

Planned Dates: M5J10 Improvement Scheme; 2020 Homes England Funding Grant Determination Agreement signing – July/August 2020 Public consultation - Autumn 2020