Ashchurch Bridge over Rail (ABoR)

Note the scheme being undertaken to design and construct a new road over rail structure at Ashchurch as part of the Tewkesbury Borough Council Garden Town Development.

Approve the provision of Professional Services through the Highway Authority to Tewkesbury Borough Council for the project management, design, procurement and construction supervision of the bridge scheme.

Decision type: Key

Reason Key: Expenditure > £500,000 and 2 Divisions affected;

Decision status: Recommendations Approved

Notice of proposed decision first published: 18/12/2019

Decision due: 29 Jan 2020 by Cabinet

Lead member: Cabinet Member - Environment and Planning

Lead director: Commissioning Director: Communities and Infrastructure

Contact: Colin Chick, Executive Director of Economy, Economy and Infrastructure Email: colin.chick@gloucestershire.gov.uk.

Consultees

Cllr Nigel Moor - Cabinet member for Fire, Planning and Infrastructure
Jonathan Dibble – TBC Garden Town Programme Lead

Scrutiny Input: SCIMB 16th December 2019

Planned Dates: Design – Ongoing Planning permission Submission – spring 2020 Procurement & Construction July 2020 to December 2021 HIF funding deadline 31/03/2022.

Decisions

Documents

  • https://www.tewkesburygardentown.co.uk/  
  • ARB01 GCC Project Proposal  
  • Atkins Project Plan