Solar Photovoltaics installation at maintained schools in Gloucestershire.

24/07/2024 - Solar Photovoltaics installation at maintained schools in Gloucestershire.

Cllr Lynden Stowe sought Cabinet approval for delegated authority to conduct a competitive procurement exercise in respect of a contract or (as appropriate) contracts for the purchase and installation of solar photovoltaic (PV) panels at selected maintained schools in Gloucestershire.

 

Having considered all of the information, Cabinet noted the report and

 

 

RESOLVED to:

 

1. Approve  the release of up to £2m from the budget approved at Full Council in February 2024 as part of 2024/25 budget to provide solar PV on selected maintained schools’ premises through the purchase and installation of the solar photovoltaic panels and associated equipment/infrastructure described in Recommendation 2 below;

2. Delegate authority to the Assistant Director of Asset Management & Property Services, in consultation with the Cabinet Member for Finance and Change, to:

a) Conduct, subject to the financial restrictions set out in the Resourcing Implications section of this report below, a competitive procurement process under the CCS (Crown Commercial Service) RM6313 Demand Management & Renewables dynamic purchasing system (DPS) for such number of contracts as may be deemed necessary for the purpose of purchasing and installing solar photovoltaic panels at all maintained schools in Gloucestershire that have applied for and been selected by the council to receive such panels and associated equipment/infrastructure.

b) Award such contract(s) to the preferred tenderer(s).