14 Gloucestershire Cycle Spine: Gloucester City Centre – Contract Procurement PDF 1 MB
Additional documents:
Decision:
Cllr David Gray, Environment and Planning, sought Cabinet approval to undertake a series of competitive procurement processes for the supply of highway construction works and to award such contracts to the preferred tenderers.
Having considered all of the information, Cabinet noted the report and
RESOLVED to:
Delegate authority to the Assistant Director for Highways and Infrastructure (in consultation with the Cabinet Member for Environment and planning) to:
1. Conduct a series of competitive procurement processes in respect of contracts for the supply of highway works in relation to the Gloucestershire Cycle Spine: Gloucester City Centre (the “Scheme”).
2. Award such contracts to the preferred tenderers.
Minutes:
14.1 Cllr David Gray, Environment and Planning, sought Cabinet approval to undertake a series of competitive procurement processes for the supply of highway construction works and to award such contracts to the preferred tenderers.
14.2 Members noted the link to the previous item and recognised the importance of the Gloucester element of the scheme. The report related to the next section of the cycle spine to be delivered and would provide sustainable travel infrastructure across Gloucester City Centre. The total funding for the scheme was secured from the Department for Transport amounting to £7,920,000.
Having considered all of the information, Cabinet noted the report and
RESOLVED to:
Delegate authority to the Assistant Director for Highways and Infrastructure (in consultation with the Cabinet Member for Environment and planning) to:
1. Conduct a series of competitive procurement processes in respect of contracts for the supply of highway works in relation to the Gloucestershire Cycle Spine: Gloucester City Centre (the “Scheme”).
2. Award such contracts to the preferred tenderers.