Decision details

Arle Court Transport Hub –Contract Procurement and Ancillary Orders

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

• To seek Cabinet approval for the Executive Director of Economy, Environment & Infrastructure to be authorised to conduct a compliant competitive tender process and to award a contract(s) in respect of Arle Court Transport Hub; and

 To award such contracts, upon the conclusion of such procurement processes, to the preferred tenderers evaluated as offering the Council the most economically advantageous tenders

Decision:

Cllr David Gray Cabinet Member for Environment and Planning sought Cabinet approval for for the Executive Director of Economy, Environment & Infrastructure to conduct a series of competitive procurement processes in respect of the contracts described in the Recommendations section of the report for the supply of construction works and advanced highways and civils works in relation to the Arle Court Transport Hub scheme; and to award such contracts, upon the conclusion of such procurement processes, to the preferred tenderers evaluated as offering the Council the most economically advantageous tenders.

 

 

Having considered all of the information, Cabinet noted the report and

.

RESOLVED to:

 

Delegate authority to the Executive Director of Economy, Environment & Infrastructure (in consultation with the Cabinet Member for Environment and Planning) to:

1. Conduct a competitive procurement process under the council’s Contractor Partnering Framework Agreement: Major Construction Works 2019, Lot 2 in respect  of a call-offcontract for the supply of construction works in relation to the Arle Court Transport Hub scheme;

 

2. Conduct a separate competitive procurement process in respect of a contract for the delivery of advanced highways and civil engineering works in relation to the Arle Court Transport Hub scheme;

 

3. Award such contract to the preferred tenderers;

 

4. Make such ancillary traffic regulation orders as are required in order to successfully implement the Arle Court Transport Hub scheme (to include, amongst other things, temporary traffic regulation orders (TTRO’s) for temporary speed limits etc. during the construction phase of the scheme).

 

 

Report author: Cabinet Member - Environment and Planning

Publication date: 21/07/2021

Date of decision: 21/07/2021

Decided at meeting: 21/07/2021 - Cabinet

Effective from: 29/07/2021