A38 Cross Keys Roundabout Capacity Improvements Contract

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Having considered all of the information, including known proposals, alternative options and reasons for the recommendations, Cabinet noted the report and

 

RESOLVED to

 

Authorise the Lead Commissioner: Highway Authority to:

 

(1)  Conduct a compliant competitive tender process for the award of a contract to a single supplier for the construction of the A38 Cross Keys Roundabout Capacity Improvements and Signalisation Scheme

 

(2)  Upon conclusion of the competitive tender process, and in consultation with the Cabinet Member for Environment and Planning, enter into a contract with the preferred provider evaluated as offering the Council best value for money for delivery of the services.  In the event that the preferred provider for the contract is either unable or unwilling to enter into that contract with the Council then the officer is authorised to enter into such contract with the next willing highest placed suitably qualified provider; and

 

(3)  Acquire land required for the scheme make any other ancillary orders that might be required to successfully implement the scheme.

 

Report author: Cabinet Member - Environment and Planning

Publication date: 11/10/2018

Date of decision: 10/10/2018

Decided at meeting: 10/10/2018 - Cabinet

Effective from: 19/10/2018