Cheltenham Cyber Business Park – Transport Mitigation and M5 Junction 10 Business Case Development

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Having considered all of the information, including known proposals, alternative options and reasons for the recommendations, Cabinet noted the report and

 

RESOLVED to:

 

(1)  Approve that the County Council becomes project promoter of the £22M Growth Deal 3 allocation for the Cheltenham Cyber Business Park transport mitigation package;

 

(2)  Approve the use of the £3.3M Growth Deal funding the County Council has already received from Government via a s31 grant to progress the preparation of the scheme business case(s) for the Cheltenham Cyber Business Park ahead of the formal funding by the GFirst LEP Board;

 

(3)  Note that a further £550K will be required during 2018/19 on the development of an Outline Business Case (OBC) for the M5 Junction 10 Housing Infrastructure Fund (HIF) bid submission to Homes England by the deadline of 1st March 2019;

 

(4)  Recommend to Council that up to £275K is allocated from the A417 Missing Link Reserve to fund the OBC for M5 Junction 10, should the County Council fail to obtain funding from the Homes England bid.

 

 