Stonehouse A419 Improvement Scheme – Contract Procurement and Ancillary Orders

To seek Cabinet approval for the Commissioning Director: Communities & Infrastructure to be authorised to conduct a compliant competitive tender process and to award a contract in respect of the A419 Improvement Scheme proposals; and

For the Commissioning Director: Communities & Infrastructure to be authorised to make any other ancillary orders that might be required to successfully implement the scheme.

Decision type: Key

Reason Key: Expenditure > £500,000 and 2 Divisions affected;

Decision status: For Determination

Notice of proposed decision first published: 13/10/2017

Decision due: 15 Nov 2017 by Cabinet

Lead member: Cabinet Member - Highways and Flood

Contact: Scott Macaulay-Lowe Email: scott.macaulay-lowe@gloucestershire.gov.uk.

Consultees

Lead Cabinet Member
Local Member (Cllr L Williams)
Stroud District Council
Stroud Town Council
Officers from across Gloucestershire County Council
Highways England
Wide range of consultees as part of the statutory consultation exercise (Police/Ambulance/Freight & Haulage associations)
Public consultation event held on 20th and 22nd June 2017 (residents, general public and businesses)

Scrutiny Input: None scheduled

Planned Dates: GCC Cabinet approval – November 2017 Detailed design start – November 2017 Detailed design end – May 2018 Issue tender documents – June 2018 Tender assessment and award – August 2018 Construction start – October 2018 Construction end – Nov 2019

Documents

  • A419 Stonehouse Improvements; Full Business Case (August 2017) http://www.gloucestershire.gov.uk/roads-parking-and-rights-of-way/major-projects/stonehouse-a419-improvements/  
  • Stonehouse A419 Improvements; Full Business Case and Due Diligence Assessment Report (August 2017)  
  • Gloucestershire Strategic Economic Plan 2014 http://www.gfirstlep.com/Our-Priorities/Our-Vision/